What happened
State Grid Tibet Electric Power restored the temporary power supply line serving the core area of Gyirong Port at 8 p.m. on September 3, according to a report from People's Daily.
The restoration followed the successful reopening of the damaged section of National Highway 216 in Gyirong, which allowed crews to begin work.
Engineers worked continuously, day and night, to repair the line despite risks including landslides and frequent falling rocks at the disaster site.
Why it matters
Restoring electricity to the core disaster area is critical for supporting rescue operations, emergency communications, and basic living conditions for affected residents and responders.
The successful power restoration also signals progress in stabilizing infrastructure after the mudslide, which is essential for the area's recovery and the reopening of the border port.
Key facts
The temporary power line serving the core area of Gyirong Port was restored on September 3 at 8 p.m.
Power was restored after the damaged section of National Highway 216 in Gyirong was reopened.
State Grid Tibet Electric Power led the repair effort, working around the clock despite landslide and rockfall risks.
What to watch next
Authorities may continue efforts to fully restore permanent power infrastructure and other essential services in the disaster-affected area.
The reopening of National Highway 216 could also help speed up delivery of relief supplies and further repairs in and around Gyirong Port.